Our Project Process

We follow different processes for different types of projects, but we always follow and quote based In Accordance to the Guideline for Professional Fees in terms of Section 34 (2) of the Architectural Profession Act, 2000 Act 44 of 2000 (“the Act”)
 
  • The Standard Service is generally divided into 6 work stages. The essential functions of each work stage relevant to the service are identified hereafter as follows:

Stage 1 – Inception

  • Receive, appraise, and report on the client’s requirements about the client’s brief;
  • Determine the site and rights, and constraints;
  • Determine budgetary constraints;
  • Determine the need for consultants;
  • Determine indicative project timelines;
  • Determine methods of contracting; and whether other statutory authority applications are required or desirable.

Stage 2 – Concept and Design Stage

  • Prepare an initial design concept and advise on:
    i the intended space provisions and planning relationships;
    ii proposed materials and intended building services; and
    iii the technical and functional characteristics of the design.
  • Check for conformity of the concept with the rights to the use of the land.
  • Consult with local and statutory authorities.
  • Review the anticipated costs of the project.
  • Review the project programme.

Stage 3 – Design Development

  • Develop all aspects of the design from concept to full development, including, but
    not limited to, construction systems, materials, fittings, and finishes selections;
  • Review the programme and budget with the client, principal consultant, or other
    consultants;
  • Coordinate other consultants’ designs into the building design;
  • Prepare design development drawings, including drafting technical details and
    material specifications;
  • Discuss and agree on the building plan application and approval requirements with the local authority;

Stage 4 – Documentation and Procurement

Stage 4.1 

  • Prepare documentation required for local authority building plan application
    submission;
  • Co-ordinate technical documentation with the consultants and complete primary co-ordination sufficient to support building plan submission;
  • Review the costing and programme with the consultants;
  • Obtain the client’s authority and submit documents for approval at the local authority.

 Stage 4.2 

  • Prepare specifications for the works;
  • Complete technical documentation sufficient for tender;
  • Obtain offers for the execution of the works;
  • Evaluate offers and recommend a successful tenderer for appointment;
  • Prepare the contract documentation and arrange the signing of the building contract by the client and the successful tenderer;
  • Complete all remaining technical and construction documentation and coordinate the same with the consultants;

    Stage 5 – Construction

    • Administer the building contract;
    • Give possession of the site to the contractor;
    • Issue construction documentation;
    • Review sub-contractor designs, shop drawings, and documentation for conformity of design intent;
    • Inspect the works for conformity with the contract documentation and acceptable quality in terms of industry standards;
    • Administer and perform the duties and obligations assigned to the principal agent in the building contract;
    • Manage the completion process of the project;
    • Assist the client in obtaining the required documentation necessary for the client to obtain the occupation certificate.

    Stage 6 – Close Out

    • Facilitate the project close-out, including the collation of the necessary documentation to effect completion, handover, and operational manual of the
      project.
    • When the contractor’s obligations to the building contract have been fulfilled, the architectural professional shall issue the certificates related to the contract
      completion.
    • Provide the client with construction record documentation and the relevant technical and contractual undertakings by the contractor and subcontractors.